Screen 27
Work Orders
12 work orders in backlog
1
SCHEDULED
5
IN PROGRESS
2
AWAITING PARTS
4
COMPLETED
Backlog
| ID | Title | Turbine | Type | Priority | Status | Assigned | Due |
|---|---|---|---|---|---|---|---|
| WO-0001 | Blade leading-edge visual inspection | WTG-002 Jaisalmer Wind Park | CONDITION BASED | P3 | COMPLETED | Site O&M Team B | 08 Sept, 06:15 pm |
| WO-0002 | Torque-check tower bolts | WTG-008 Jaisalmer Wind Park | CONDITION BASED | P1 | AWAITING PARTS | Contractor - VertiCare | 07 Sept, 06:15 pm |
| WO-0003 | Brake pad replacement | WTG-026 Tirunelveli Ridge | PREVENTIVE | P2 | IN PROGRESS | Site O&M Team A | 06 Sept, 06:15 pm |
| WO-0004 | Replace pitch bearing grease seal | WTG-014 Kutch Wind Corridor | CONDITION BASED | P2 | IN PROGRESS | Site O&M Team B | 09 Sept, 06:15 pm |
| WO-0005 | Yaw drive inspection | WTG-010 Jaisalmer Wind Park | PREVENTIVE | P2 | COMPLETED | Contractor - VertiCare | 16 Sept, 06:15 pm |
| WO-0006 | Blade leading-edge visual inspection | WTG-006 Jaisalmer Wind Park | CONDITION BASED | P1 | SCHEDULED | Contractor - VertiCare | 06 Sept, 06:15 pm |
| WO-0007 | Torque-check tower bolts | WTG-047 Anantapur Flats | PREVENTIVE | P3 | IN PROGRESS | Site O&M Team A | 05 Sept, 06:15 pm |
| WO-0008 | Converter fan replacement | WTG-031 Chitradurga Plateau | CORRECTIVE | P3 | AWAITING PARTS | Contractor - VertiCare | 12 Sept, 06:15 pm |
| WO-0009 | Yaw drive inspection | WTG-017 Kutch Wind Corridor | CORRECTIVE | P2 | IN PROGRESS | Site O&M Team A | 13 Sept, 06:15 pm |
| WO-0010 | Yaw drive inspection | WTG-038 Satara Ghats | CORRECTIVE | P1 | COMPLETED | Site O&M Team A | 05 Sept, 06:15 pm |
| WO-0011 | Gearbox oil sample & analysis | WTG-022 Tirunelveli Ridge | CONDITION BASED | P1 | COMPLETED | Contractor - VertiCare | 08 Sept, 06:15 pm |
| WO-0012 | Comms gateway reboot & firmware check | WTG-017 Kutch Wind Corridor | PREVENTIVE | P1 | IN PROGRESS | OEM Service Partner | 15 Sept, 06:15 pm |